WASTEWATER TREATMENT PLANT UPDATE

Each monthly meeting the board and all attending residents are updated on the progress of the new wastewater treatment facility. As of May 2022 the plant is on schedule to be completed in the summer of 2023.

Due to annexations and home growth in the area for both Greenwood UD and Parkway UD a larger facility was needed to accommodate a higher capacity. The new plant will expand the capacity from .95 MGD to 1.875 MGD. The construction is headed by CSA Construction and was issued a notice to proceed in March 2021.

Have questions or concerns about the new wastewater treatment plant?

Contact Greenwood UD with your concerns. Public comments are taken at the beginning of each monthly meeting held on the third Wednesday at 6:30PM if you prefer to make your comments to the board in person.